The Kmart Corporation selected Primus Builders to renovate their existing facility. The scope of this project was to demolish approximately 160,000 SF of existing enclosed truck concourse and convert into an open yard shipping and receiving operation to handle the 52” trailers.

Primus installed 120 new, state-of-the-art dock positions with break-out doors, automatic dock boards, communications systems, trailer ventilation, lighting package and vehicle restraints.

This project increased shipping productivity and limited the need for Kmart to move the over-the-road cargo with yard trucks.

In order to keep Kmart in full operation, the work was staged into seven phases to allow the facility to maintain inventory in the stores.
   
< Back  
NEWSLETTERpanels
FEATURED CASE STUDIES:
- GOLD'S GYM (Woodstock, GA)
- CLIFTON-DEKALB (Atlanta, GA)
- KABOB'S, INC (Lake City, GA)
- KMART CORPORATION (Newnan, GA)
CASE STUDY ARCHIVES:
2008: Gold's Gym / Knowledge Points Learning Center / Peachtree Aviation / Steris Corporation
TESTIMONIALS:
Testimonial - Barbara Wheeler (Education Ventures)
TONY PITRONE - VP of Business Dev.
Tony is responsible for sales strategies,
and management of large clients.
MATT HIRSCH - Vice President of Sales
Matt is responsible for sales strategies, managing large clients and partnerships.
© 2012 PRIMUS BUILDERS. All Rights Reserved

Safety Resources
Employee Resources Login
AJC